Update
The installation of the Hydrogen Office Wind Turbine ran smoothly and the fit out works are due to be completed shortly; though due to delays in securing the grid connection and the new transformer, the turbine will not be operational for a number of weeks.
Blades being lifted onto the Nacelle
The Nacelle being lifted on top of the second tower section
The first tower section being lifted into place
The foundation work being undertaken
The Turbine was supplied by Global Wind Power (GWP) and can be seen sailing over from India.