2009 Progress Update
Wednesday 11th February 2009.
The development of the Hydrogen Office Ltd is well underway with building work due to be completed in March 2009.
Torith, the project’s contractor has now started the final fitting out phase of the main building work contract, and work will soon commence on the installation of the hydrogen fuel cell system. Work on the innovative heating system is also nearing completion (see news story posted 6th Feb 09).
The Hydrogen Office is in discussions with a wind turbine supplier and hopes to be able to conclude these discussions shortly.
Figures 1 and 2 show the comparison before and during construction work at the Energy Park in Methil, Fife.
Figure 1 - The site before building work commenced (2007)
Figure 2 - the site in January 2009.